In a workflow template, what is transferred by ports among the workflow's activities?
The correct answer is A. package. See the full explanation below for the reasoning.
Question
In a workflow template, what is transferred by ports among the workflow's activities?
Options
- Apackage
- Busers
- Caliases
- Dgroups
How the community answered
(20 responses)- A75% (15)
- B5% (1)
- C5% (1)
- D15% (3)