Dell-EMC
E10-002 · Question #37
Which activity is carried out during the `Plan' step of the service enablement roadmap?
The correct answer is A. Analyzing the gap between existing IT capability and expected IT capability. See the full explanation below for the reasoning.
Question
Which activity is carried out during the `Plan' step of the service enablement roadmap?
Options
- AAnalyzing the gap between existing IT capability and expected IT capability
- BUnderstanding the business value that the services can bring
- COptimizing the cloud infrastructure and services to an evolving business strategy
- DTransforming the existing IT infrastructure to deliver services as planned
How the community answered
(20 responses)- A75% (15)
- B5% (1)
- C15% (3)
- D5% (1)
Community Discussion