nerdexam
Dell-EMC

E10-002 · Question #133

Which management process ensures business continuity by eliminating single points of failure in a data center?

The correct answer is C. Capacity management. See the full explanation below for the reasoning.

Question

Which management process ensures business continuity by eliminating single points of failure in a data center?

Options

  • AAvailability management
  • BSecurity management
  • CCapacity management
  • DPerformance management

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    3% (1)
  • C
    79% (27)
  • D
    6% (2)

Community Discussion

No community discussion yet for this question.

Full E10-002 Practice