Dell-EMC
E10-001 · Question #340
When deploying a cold backup solution, what should be considered?
The correct answer is A. Application must be shut down during the backup process. See the full explanation below for the reasoning.
Question
When deploying a cold backup solution, what should be considered?
Options
- AApplication must be shut down during the backup process
- BApplication can only read the data to be backed up
- CAn open file agent must be deployed to perform the backup
- DDeduplication cannot be performed during the backup process
How the community answered
(22 responses)- A77% (17)
- B5% (1)
- C14% (3)
- D5% (1)