E10-001 · Question #312

A system has three components and all three components need to be operational for 24 hours; Monday to Friday. During a particular week, failure of component 2 occurred as follows: - Monday = 6 PM to…

The correct answer is B. 38 Hours. See the full explanation below for the reasoning.

Question

A system has three components and all three components need to be operational for 24 hours; Monday to Friday. During a particular week, failure of component 2 occurred as follows:

  • Monday = 6 PM to 9 PM
  • Tuesday = 8 AM to 10 AM
  • Wednesday = No failure
  • Thursday = 8 PM to 9 PM
  • Friday = No failure
  • Saturday = 5 AM to 8 AM
  • Sunday = 6 PM to 9 PM

What is the mean time between failures on component 2?

Options

  • A30 Hours
  • B38 Hours
  • C40 Hours
  • D42 Hours

How the community answered

(43 responses)
  • A
    9% (4)
  • B
    84% (36)
  • C
    5% (2)
  • D
    2% (1)