A system has three components and all three components need to be operational for 24 hours; Monday to Friday. During a particular week, failure of component 2 occurred as follows: - Monday = 6 PM to…
Sign in or unlock E10-001 to reveal the answer and full explanation for question #312. The question stem and answer options stay visible for context.
Question
A system has three components and all three components need to be operational for 24 hours; Monday to Friday. During a particular week, failure of component 2 occurred as follows:
- Monday = 6 PM to 9 PM
- Tuesday = 8 AM to 10 AM
- Wednesday = No failure
- Thursday = 8 PM to 9 PM
- Friday = No failure
- Saturday = 5 AM to 8 AM
- Sunday = 6 PM to 9 PM
What is the mean time between failures on component 2?
Options
- A30 Hours
- B38 Hours
- C40 Hours
- D42 Hours