Question
A system has three components and all three components need to be operational 24 hours; Monday to Friday. During a particular week, failure of component 3 occurred as follows:
- Monday = 6 PM to 9 PM
- Tuesday = 8 AM to 10 AM
- Wednesday = No failure
- Thursday = 8 PM to 9 PM
- Friday = No failure
- Saturday = 5 AM to 8 AM
- Sunday = 6 PM to 9 PM
What is the mean time to repair component 3?
Options
- A2 Hours
- B4 Hours
- C6 Hours
- D8 Hours