DY0-001 · Question #94

A data scientist has constructed a model that meets the minimum performance requirements specified in the proposal for a prediction project. The data scientist thinks the model's accuracy should be…

The correct answer is C. Consult the key project stakeholder. Since the model already meets the agreed-upon requirements and the deadline is near, the first step is to confirm with the stakeholder whether pursuing further accuracy gains is worth the additional time and resources. This ensures you align with business priorities before…

Operations and Processes

Question

A data scientist has constructed a model that meets the minimum performance requirements specified in the proposal for a prediction project. The data scientist thinks the model's accuracy should be improved, but the proposed deadline is approaching. Which of the following actions should the data scientist take first?

Options

  • AContinue collecting data.
  • BRequest additional funding.
  • CConsult the key project stakeholder.
  • DTest additional model specifications.

How the community answered

(32 responses)
  • A
    34% (11)
  • B
    6% (2)
  • C
    47% (15)
  • D
    13% (4)

Explanation

Since the model already meets the agreed-upon requirements and the deadline is near, the first step is to confirm with the stakeholder whether pursuing further accuracy gains is worth the additional time and resources. This ensures you align with business priorities before collecting more data, requesting funding, or tweaking the model further.

Topics

#stakeholder communication#project management#model performance#deadline management