nerdexam
APC

DU0-001 · Question #207

What is an indirect cost of downtime that is difficult to quantify?

The correct answer is D. Damaged brand perception. See the full explanation below for the reasoning.

Data Center Management and Operations

Question

What is an indirect cost of downtime that is difficult to quantify?

Options

  • ALegal fees
  • BLost revenues
  • CIdle employees
  • DDamaged brand perception

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    11% (4)
  • D
    80% (28)

Topics

#indirect costs#brand perception#downtime impact#cost quantification

Community Discussion

No community discussion yet for this question.