Which scenario illustrates a data center's agility?
The correct answer is C. A data center is designed with interchangeable power distribution. Interchangeable power distribution (C) demonstrates agility because it allows a data center to quickly swap, upgrade, or reconfigure components without redesigning the entire infrastructure - adapting rapidly to changing operational demands. This flexibility to modify and…
Question
Options
- AA data center is built out to final design capacity.
- BA data center is designed with one hour of runtime.
- CA data center is designed with interchangeable power distribution.
- DA data center is configured with 50% AC power and 50% DC power in anticipation of loads.
How the community answered
(23 responses)- A4% (1)
- B17% (4)
- C70% (16)
- D9% (2)
Explanation
Interchangeable power distribution (C) demonstrates agility because it allows a data center to quickly swap, upgrade, or reconfigure components without redesigning the entire infrastructure - adapting rapidly to changing operational demands. This flexibility to modify and evolve is the essence of agility.
Why the others are wrong:
- A - Building to final design capacity is the opposite of agility; it locks the data center into a fixed state with no room to adapt.
- B - One hour of runtime describes resiliency (or lack thereof), not the ability to change quickly.
- D - Pre-splitting AC/DC loads reflects planning or scalability anticipation, not the capacity to rapidly reconfigure in response to change.
Memory tip: Link "agility" to "interchangeable" - just as an agile athlete can pivot quickly, interchangeable components let a data center pivot its design without starting over. If you see "fixed," "final," or "anticipated" in an answer, that's rigidity, not agility.