DS0-001 · Question #9
Which of the following is the correct order of the steps in the database deployment process?
The correct answer is C. 1. Confirm prerequisites. The correct deployment process begins with (1) Confirm prerequisites - verifying that all system requirements (OS version, disk space, memory, dependencies, licenses) are met before attempting installation. Attempting to install without confirming prerequisites wastes time and ri
Question
Which of the following is the correct order of the steps in the database deployment process?
Options
- A
- Connect
- B
- Configure
- C
- Confirm prerequisites
- D
- Install
How the community answered
(47 responses)- A4% (2)
- B2% (1)
- C91% (43)
- D2% (1)
Explanation
The correct deployment process begins with (1) Confirm prerequisites - verifying that all system requirements (OS version, disk space, memory, dependencies, licenses) are met before attempting installation. Attempting to install without confirming prerequisites wastes time and risks partial installs. The full typical order is: Confirm prerequisites → Install → Configure → Connect (test connectivity). Choice D starts with Install, which skips the prerequisite check. Choice B starts with Configure, which cannot happen before installation. Choice A starts with Connect, which is the last validation step.