The correct answer is C: 1. Confirm prerequisites. This order follows the best practices for deploying a database system, which are: Confirm prerequisites: Check the system requirements and compatibility of the database software and tools before installation. Install: Install the database software and tools on the target server o

Database Deployment

Question

Which of the following is the correct order of the steps in the database deployment process?

Options

  • A1. Connect
  • B1. Configure
  • C1. Confirm prerequisites
  • D1. Install

Explanation

This order follows the best practices for deploying a database system, which are: Confirm prerequisites: Check the system requirements and compatibility of the database software and tools before installation. Install: Install the database software and tools on the target server or platform. Configure: Configure the database settings and parameters according to the specifications and needs of the application or organization. Connect: Connect the database to the network and other systems or applications that will access Test: Test the functionality and performance of the database system and verify that it meets the expectations and requirements. Validate: Validate the data quality and integrity of the database system and ensure that it complies with the standards and regulations. Release: Release the database system to production and make it available for use by end-users The other options do not follow this order and may result in errors, inefficiencies, or security

Topics

#Database deployment#Deployment process#Prerequisite checking

Community Discussion

No community discussion yet for this question.

Full DS0-001 PracticeBrowse All DS0-001 Questions