nerdexam
MicrosoftMicrosoft

DP-600 · Question #78

DP-600 Question #78: Real Exam Question with Answer & Explanation

The correct answer is B: Upon Completion. To ensure a subsequent activity executes regardless of whether the preceding activity succeeds or fails, configure an 'Upon Completion' conditional path.

Submitted by wei.xz· Apr 18, 2026Plan, implement, and manage a solution for data analytics

Question

You have a Fabric tenant. You plan to create a data pipeline named Pipeline1. Pipeline1 will include two activities that will execute in sequence. You need to ensure that a failure of the first activity will NOT block the second activity. Which conditional path should you configure between the first activity and the second activity?

Options

  • AUpon Failure
  • BUpon Completion
  • CUpon Skip
  • DUpon Skip

Explanation

To ensure a subsequent activity executes regardless of whether the preceding activity succeeds or fails, configure an 'Upon Completion' conditional path.

Common mistakes.

  • A. An 'Upon Failure' path would only execute the second activity if the first activity explicitly failed, not if it succeeded.
  • C. An 'Upon Skip' path would only execute if the first activity was skipped, which is not the scenario described where the activity either succeeds or fails.
  • D. An 'Upon Skip' path is incorrect for the same reason as option C.

Concept tested. Data pipeline activity dependencies and conditional execution

Reference. https://learn.microsoft.com/en-us/fabric/data-factory/pipeline-activities-overview

Topics

#Microsoft Fabric#Data Pipelines#Activity Dependencies#Conditional Paths

Community Discussion

No community discussion yet for this question.

Full DP-600 PracticeBrowse All DP-600 Questions