An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?
The correct answer is D. Power distribution must support the power rating of all nodes. See the full explanation below for the reasoning.
Question
An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?
Options
- ASingle power zone must be used with adequate power cables
- BAt least 24 in (61 cm) of clearance must exist in front of and behind the cabinet
- CService laptop must be on the same IP network as the iDRACs
- DPower distribution must support the power rating of all nodes
How the community answered
(50 responses)- A12% (6)
- B6% (3)
- C2% (1)
- D80% (40)