An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?
The correct answer is B. Redundant power zones exist with adequate power cables. See the full explanation below for the reasoning.
Question
An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?
Options
- AAt least 24 in (61 cm) of clearance exists in front of and behind the cabinet
- BRedundant power zones exist with adequate power cables
- CPower distribution supports only the power rating of a single node
- DService laptop is on the same IP network as the iDRACs
How the community answered
(43 responses)- A19% (8)
- B70% (30)
- C9% (4)
- D2% (1)