DES-6322 · Question #43
DES-6322 Question #43: Real Exam Question with Answer & Explanation
Sign in or unlock DES-6322 to reveal the answer and full explanation for question #43. The question stem and answer options stay visible for context.
Question
An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?
Options
- AService laptop must be on the same IP network as the iDRACs
- BAt least 36 in (92 cm) clearance exists in front of and behind the cabinet
- CPower distribution must support the power rating of a single node
- DSingle power zone must be used with adequate power cables
Unlock DES-6322 to see the answer
You've previewed enough free DES-6322 questions. Unlock DES-6322 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.