An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?

The correct answer is C. Power distribution must support the power rating of a single node. See the full explanation below for the reasoning.

Question

An implementation engineer is deploying a new VxRail cluster. What should they confirm before installing the hardware?

Options

  • AService laptop must be on the same IP network as the iDRACs
  • BAt least 36 in (92 cm) clearance exists in front of and behind the cabinet
  • CPower distribution must support the power rating of a single node
  • DSingle power zone must be used with adequate power cables

How the community answered

(30 responses)
  • A
    3% (1)
  • B
    13% (4)
  • C
    77% (23)
  • D
    7% (2)

Community Discussion

No community discussion yet for this question.