A Dell EMC solutions architect has updated the VxRail PEQ with Customer Top-of-Rack (ToR) switch details. On which worksheet would they need to be to generate a new NVT JSON file?

The correct answer is D. VxRail Cluster. See the full explanation below for the reasoning.

Question

A Dell EMC solutions architect has updated the VxRail PEQ with Customer Top-of-Rack (ToR) switch details. On which worksheet would they need to be to generate a new NVT JSON file?

Options

  • AEngagement Details
  • BNetworking Details
  • CCustomer
  • DVxRail Cluster

How the community answered

(36 responses)
  • A
    3% (1)
  • B
    8% (3)
  • C
    17% (6)
  • D
    72% (26)