A technician installs eight servers into a fully operational rack with top of rack switch. Each server has a quad 1Gb NIC and redundant power supplies. The company uses iDRAC in shared LOM mode with…
The correct answer is C. iDRAC dedicated NIC port is cabled and the link light is green. See the full explanation below for the reasoning.
Question
A technician installs eight servers into a fully operational rack with top of rack switch. Each server has a quad 1Gb NIC and redundant power supplies. The company uses iDRAC in shared LOM mode with LOM1 as the selected NIC. What should the technician do to verify iDRAC connectivity on each server?
Options
- AiDRAC Datacenter license is installed.
- BEthernet port LOM1 is cabled and the link light is green.
- CiDRAC dedicated NIC port is cabled and the link light is green
- DiDRAC Enterprise license is installed
How the community answered
(21 responses)- B5% (1)
- C86% (18)
- D10% (2)
Community Discussion