Your company recently negotiated several contracts with new customers to use its proprietary eCommerce system. As a result, the customer base has grown rapidly, which has introduced several…
The correct answer is C. $ 117,000. See the full explanation below for the reasoning.
Question
Your company recently negotiated several contracts with new customers to use its proprietary eCommerce system. As a result, the customer base has grown rapidly, which has introduced several challenges and requirements.
Business requirements:
Applications need to scale quickly
Metrics and reporting to anticipate business trends and efficient use of resources
External customers are looking to license the eCommerce application
Other considerations:
Applications need to be recorded for the public cloud
Address security vulnerabilities for customer data in the cloud
You are tasked with designing a cloud. You review the existing infrastructure and business requirements. You select a CI solution to replace the existing Platform 2.0 infrastructure. Before presenting this solution to the company, you must calculate the 3-year TCO using the following criteria:
Hardware maintenance = $ 35,000
Software maintenance = $ 20,000
Storage = $ 2,000 (2TB @ $ 1/GB)
What is the correct TCO value?
Options
- A$ 97,000
- B$ 67,000
- C$ 117,000
- D$ 83,000
How the community answered
(38 responses)- A16% (6)
- B8% (3)
- C74% (28)
- D3% (1)