DES-2T13 · Question #16

You are analyzing the performance data to avoid oversizing of a CI solution. What date and time frame should you use?

The correct answer is D. Peak production times over a single day. See the full explanation below for the reasoning.

Question

You are analyzing the performance data to avoid oversizing of a CI solution. What date and time frame should you use?

Options

  • AAverage production time over multiple days
  • BPeak production time over multiple days
  • CAverage production time over a single day
  • DPeak production times over a single day

How the community answered

(30 responses)
  • A
    7% (2)
  • B
    13% (4)
  • C
    7% (2)
  • D
    73% (22)