You are analyzing the performance data to avoid oversizing of a CI solution. What date and time frame should you use?
The correct answer is D. Peak production times over a single day. See the full explanation below for the reasoning.
Question
You are analyzing the performance data to avoid oversizing of a CI solution. What date and time frame should you use?
Options
- AAverage production time over multiple days
- BPeak production time over multiple days
- CAverage production time over a single day
- DPeak production times over a single day
How the community answered
(30 responses)- A7% (2)
- B13% (4)
- C7% (2)
- D73% (22)
Community Discussion