When sizing a Dell EMC Unity Hybrid array, what are considerations for growth?
The correct answer is D. General capacity and active data. Considerations for capacity growth - (click) Overall growth vs active data growth - (click) Moving or expanding "hot blocks" of active data - Longer term planning for growth
Midrange Storage Solutions Planning and Design
Question
When sizing a Dell EMC Unity Hybrid array, what are considerations for growth?
Options
- APort utilization and load balancing
- BCache utilization and hardware bottlenecks
- CLatency and queue depth
- DGeneral capacity and active data
How the community answered
(31 responses)- A6% (2)
- B3% (1)
- C16% (5)
- D74% (23)
Explanation
Considerations for capacity growth - (click) Overall growth vs active data growth - (click) Moving or expanding "hot blocks" of active data - Longer term planning for growth