A company has an existing 8-node F800 Isilon cluster with two Z9100 Dell Ethernet back-end switches running on OneFS 8.2.0. The company is planning to add 72 A200 nodes into the cluster. What is the…

The correct answer is A. 2. See the full explanation below for the reasoning.

Question

A company has an existing 8-node F800 Isilon cluster with two Z9100 Dell Ethernet back-end switches running on OneFS 8.2.0. The company is planning to add 72 A200 nodes into the cluster. What is the minimum number of additional switches required to support the configuration?

Options

  • A2
  • B3
  • C4
  • D6

How the community answered

(42 responses)
  • A
    83% (35)
  • B
    10% (4)
  • C
    5% (2)
  • D
    2% (1)