Question

The administrator receives an alert on a PowerStore Cluster with three appliances: Estimated time to fill is projected to run out of space in 8 days Capacity utilization is above 90 percent Which tools are available to assist the Administrator with a potential resolution?

Options

  • AThin provision conversion wizard
  • BSystem Optimization
  • CSystem Expansion wizard
  • DAssisted Migration

Unlock DES-1221 to see the answer