Which activity needs to be performed prior to the operations shown in the exhibit?
The correct answer is A. TTL setting should be changed. See the full explanation below for the reasoning.
Question
Which activity needs to be performed prior to the operations shown in the exhibit?
Exhibit
Options
- ATTL setting should be changed
- BSnapshot should be terminated
- CTarget volumes should be unmounted
- DTarget volumes should be unmapped
How the community answered
(64 responses)- A72% (46)
- B14% (9)
- C5% (3)
- D9% (6)