DEE-1421 · Question #29

A company is planning to replicate a dataset to a newly implemented Dell EMC Isilon cluster. SyncIQ will be used from the source cluster to the target cluster. The company's systems administrator…

The correct answer is A. 10. See the full explanation below for the reasoning.

Question

A company is planning to replicate a dataset to a newly implemented Dell EMC Isilon cluster. SyncIQ will be used from the source cluster to the target cluster. The company’s systems administrator wants to know how long the initial synchronization will take without seeding. The administrator provides the following information:

Link speed between clusters is 1 Gb/s  Link speed efficiency is 85%  SyncIQ domain size is 125TB  If no SyncIQ performance rules are set, what is the estimated number of days?

Options

  • A10
  • B12
  • C14
  • D16

How the community answered

(62 responses)
  • A
    77% (48)
  • B
    3% (2)
  • C
    13% (8)
  • D
    6% (4)

Community Discussion

No community discussion yet for this question.