Dell-EMC
DEE-1421 · Question #24
A company is implementing Superna Eyeglass to automate and orchestrate SyncIQ failover and failback. What is one of the requirements when implementing Superna Eyeglass for a Dell EMC Isilon cluster?
The correct answer is C. Dedicated subnet must exist. See the full explanation below for the reasoning.
Question
A company is implementing Superna Eyeglass to automate and orchestrate SyncIQ failover and failback. What is one of the requirements when implementing Superna Eyeglass for a Dell EMC Isilon cluster?
Options
- ADedicated IP pool must exist
- BAdministrator account must be used
- CDedicated subnet must exist
- DSystem Access zone must be used
How the community answered
(64 responses)- A8% (5)
- B13% (8)
- C77% (49)
- D3% (2)
Community Discussion