DEE-1421 · Question #11

A company is planning to add eight additional nodes to their existing 4-node Dell EMC Isilon cluster. If the administrator plans to add all eight nodes at the same time without causing any outage…

The correct answer is B. All nodes will be added without errors. See the full explanation below for the reasoning.

Question

A company is planning to add eight additional nodes to their existing 4-node Dell EMC Isilon cluster. If the administrator plans to add all eight nodes at the same time without causing any outage, what is the result of this action?

Options

  • AOneFS will not proceed with the addition
  • BAll nodes will be added without errors
  • CAll nodes will be added with errors
  • DQuorum will be lost

How the community answered

(22 responses)
  • A
    5% (1)
  • B
    77% (17)
  • C
    14% (3)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.