You are assisting a company in planning for a Dell EMC Isilon disaster recovery site. One of the company's concerts is the time that is needed for the initial synchronization between the primary and…

The correct answer is D. After creating the policies, start the job and observe how much time it takes. See the full explanation below for the reasoning.

Question

You are assisting a company in planning for a Dell EMC Isilon disaster recovery site. One of the company’s concerts is the time that is needed for the initial synchronization between the primary and disaster recovery sites. What will help address this concern?

Options

  • AAfter creating the policies, use the "assess sync" functionality
  • BUse a third-party tool to estimate the time based on the data and the bandwidth
  • CTime cannot be estimated due to many factors such as the cluster workload
  • DAfter creating the policies, start the job and observe how much time it takes

How the community answered

(41 responses)
  • A
    2% (1)
  • B
    12% (5)
  • C
    5% (2)
  • D
    80% (33)

Community Discussion

No community discussion yet for this question.

Full DEE-1421 Practice