Dell-EMC
DEA-64T1 · Question #19
A software development company wants to refresh their existing infrastructure. One of their goals is to enable faster development times for their products. The development teams indicate that their…
The correct answer is A. VxBlock 500. See the full explanation below for the reasoning.
Question
A software development company wants to refresh their existing infrastructure. One of their goals is to enable faster development times for their products. The development teams indicate that their biggest delays are caused by having to wait for the infrastructure teams to provision new VMs and networks for test environments. Which Dell EMC platform would meet all of the company's requirements without the addition of optional components?
Options
- AVxBlock 500
- BVxRack FLEX
- CVxRack SDDC
- DVxRail
How the community answered
(18 responses)- A83% (15)
- C6% (1)
- D11% (2)
Community Discussion
No community discussion yet for this question.