DEA-2TT3 · Question #49
The incident management team is unable to determine the root cause of an incident. To which team should the error-correction activity be transferred?
The correct answer is D. Problem Management. See the full explanation below for the reasoning.
Question
The incident management team is unable to determine the root cause of an incident. To which team should the error-correction activity be transferred?
Options
- APerformance Management
- BChange Management
- CAvailability Management
- DProblem Management
How the community answered
(45 responses)- A4% (2)
- B16% (7)
- C9% (4)
- D71% (32)