Dell-EMC
DEA-1TT5 · Question #72
A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 1 occurred as follows: -Tuesday = 8…
The correct answer is B. 37 hours. See the full explanation below for the reasoning.
Question
A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 1 occurred as follows:
-Tuesday = 8 AM to 11 AM -Thursday = 8 PM to 10 PM -Friday = 5 AM to 9 AM What is the mean time between failures on component 1 for that week?
Options
- A3 hours
- B37 hours
- C40 hours
- D53 hours
How the community answered
(40 responses)- A5% (2)
- B83% (33)
- C3% (1)
- D10% (4)
Community Discussion
No community discussion yet for this question.