nerdexam
Dell-EMC

DEA-1TT4 · Question #71

A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 3 occurred as follows: -Tuesday = 8…

The correct answer is B. 35 hours. See the full explanation below for the reasoning.

Question

A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 3 occurred as follows:

-Tuesday = 8 AM to 1 PM -Thursday = 5 PM to 10 PM -Friday = 5 AM to 10 AM What is the mean time between failures on component 3 for that week?

Options

  • A5 hours
  • B35 hours
  • C40 hours
  • D51 hours

How the community answered

(22 responses)
  • A
    14% (3)
  • B
    73% (16)
  • C
    5% (1)
  • D
    9% (2)

Community Discussion

No community discussion yet for this question.

Full DEA-1TT4 Practice