Dell-EMC
D-PSC-DS-23 · Question #121
A North-American based customer has an existing six node A2000 cluster installed in a Titan-HD rack, using ten rack units. The customer would like to add a new F800 node tier to their cluster. Their…
The correct answer is C. Step-up transformers are required. See the full explanation below for the reasoning.
Question
A North-American based customer has an existing six node A2000 cluster installed in a Titan-HD rack, using ten rack units. The customer would like to add a new F800 node tier to their cluster. Their data center uses under-floor cooling and single-phase power. What is a consideration when installing the F800 nodes?
Options
- AThe F800 nodes will not fit in a Titan-HD rack.
- BTwo F800 nodes can be added to the open node slots.
- CStep-up transformers are required.
- DA2000 backend ports are incompatible with the F800.
How the community answered
(30 responses)- A17% (5)
- B3% (1)
- C70% (21)
- D10% (3)
Community Discussion
No community discussion yet for this question.