D-ISM-FN-23 · Question #337

A Fibre Channel switch has eight ports and all ports must be operational 24 hours 7 days. However, a failure of Port 5 occurs on a particular week as follows: Monday = 11 AM to 3 PM Thursday = 6 AM…

The correct answer is A. 91.6%. IA = Downtime/(DownTime+Uptime) = 154/168 =0.916 X 100 = 91.6%

Storage Networking Technologies

Question

A Fibre Channel switch has eight ports and all ports must be operational 24 hours 7 days. However, a failure of Port 5 occurs on a particular week as follows:

Monday = 11 AM to 3 PM Thursday = 6 AM to 11 AM Saturday = 11 AM to 4 PM What is the availability of Port 5 in that week?

Options

  • A91.6%
  • B94.6%
  • C95%
  • D90%

How the community answered

(32 responses)
  • A
    75% (24)
  • B
    16% (5)
  • C
    6% (2)
  • D
    3% (1)

Explanation

IA = Downtime/(DownTime+Uptime) = 154/168 =0.916 X 100 = 91.6%

Topics

#availability calculation#Fibre Channel#port availability#uptime

Community Discussion

No community discussion yet for this question.