A Fibre Channel switch has eight ports and all ports must be operational 24x7. However, a failure of Port 5 occurs on a particular week as follows: - Monday = 11 AM to 12 PM - Thursday = 7 AM to 11…

The correct answer is C. 95.8%. See the full explanation below for the reasoning.

Storage System Environment

Question

A Fibre Channel switch has eight ports and all ports must be operational 24x7. However, a failure of Port 5 occurs on a particular week as follows:

  • Monday = 11 AM to 12 PM
  • Thursday = 7 AM to 11 AM
  • Saturday = 11 AM to 1 PM

What is the availability of Port 5 in that week?

Options

  • A93%
  • B94.1%
  • C95.8%
  • D97%

How the community answered

(61 responses)
  • A
    5% (3)
  • B
    8% (5)
  • C
    72% (44)
  • D
    15% (9)