A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 3 occurred as follows: - Tuesday = 8…

The correct answer is B. 35 hours. See the full explanation below for the reasoning.

Storage Management

Question

A system has three components and all three components need to be operational for 24 hours; Monday through Friday. During a particular week, failure of component 3 occurred as follows:

  • Tuesday = 8 AM to 1 PM
  • Thursday = 5 PM to 10 PM
  • Friday = 5 AM to 10 AM

What is the mean time between failures on component 3 for that week?

Options

  • A5 hours
  • B35 hours
  • C40 hours
  • D51 hours

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    77% (27)
  • C
    6% (2)
  • D
    14% (5)

Topics

#MTBF#availability calculation#component reliability#failure analysis