What is the result of increasing the number of FC switches in a full mesh topology?
The correct answer is C. Reduces switch ports available for node connectivity. See the full explanation below for the reasoning.
Storage Networking Technologies
Question
What is the result of increasing the number of FC switches in a full mesh topology?
Options
- AReduces available node ports for ISL connectivity
- BReduces number of storage and compute ports for node connectivity
- CReduces switch ports available for node connectivity
- DReduces switch ports available bandwidth for node connectivity
How the community answered
(20 responses)- A15% (3)
- B5% (1)
- C70% (14)
- D10% (2)