A system has three components, and all three components need to be operational from 8 AM to 5 PM; Monday to Friday. During a particular week, failure of component 3 occurred as follows: Monday = 7…

The correct answer is B. 86.6%. See the full explanation below for the reasoning.

Data Protection

Question

A system has three components, and all three components need to be operational from 8 AM to 5 PM; Monday to Friday. During a particular week, failure of component 3 occurred as follows:

Monday = 7 AM to 11 AM Tuesday = No failure Wednesday = 4 PM to 7 PM Thursday = No failure Friday = 12 PM to 2 PM Saturday = 5 AM to 8 AM Sunday = 6 PM to 9 PM What is the availability of component 3 for this week?

Options

  • A84.2%
  • B86.6%
  • C90.8%
  • D92.4%

How the community answered

(60 responses)
  • A
    2% (1)
  • B
    85% (51)
  • C
    8% (5)
  • D
    5% (3)

Topics

#availability calculation#component availability#business hours downtime#service window