D-CSF-SC-01 · Question #130

The project manager of a data center has a budget of $1,500,000 to install critical infrastructure systems. The project will take 24 months to complete. The project manager is working with the…

The correct answer is B. Update the company risk register. See the full explanation below for the reasoning.

Question

The project manager of a data center has a budget of $1,500,000 to install critical infrastructure systems. The project will take 24 months to complete. The project manager is working with the project management team, security experts, and stakeholders to identify cyber risks. After reviewing the project plan, the CIO wants to know why so many risk identification meetings are requested. What a valid reason for the repeated risk identification meetings?

Options

  • AIdentify new risks
  • BUpdate the company risk register
  • CTransfer risk to other project team members
  • DPrevent all risk

How the community answered

(37 responses)
  • A
    8% (3)
  • B
    73% (27)
  • C
    16% (6)
  • D
    3% (1)