CWNA-107 · Question #3

You are using a site survey tool for post-implementation validation. You have installed the appropriate adapter driver and imported a floor plan. Now, you want to take the next step in proper tool…

The correct answer is C. Calibrate the floor plan. See the full explanation below for the reasoning.

Question

You are using a site survey tool for post-implementation validation. You have installed the appropriate adapter driver and imported a floor plan. Now, you want to take the next step in proper tool use. What must you do before gathering survey data after the floor plan is imported?

Options

  • AInstall iPerf
  • BInstall WinPCAP
  • CCalibrate the floor plan
  • DNothing, you can simply start capturing signal readings

How the community answered

(34 responses)
  • A
    12% (4)
  • B
    3% (1)
  • C
    82% (28)
  • D
    3% (1)