CWNP
CWDP-305 · Question #86
What action should be taken after implementing a WLAN based on the design developed from the site survey process?
The correct answer is A. Post-installation survey. See the full explanation below for the reasoning.
Question
What action should be taken after implementing a WLAN based on the design developed from the site survey process?
Options
- APost-installation survey
- BRequirements analysis
- CGathering facility documentation
- DDesign the infrastructure services
How the community answered
(29 responses)- A79% (23)
- B3% (1)
- C7% (2)
- D10% (3)
Community Discussion
No community discussion yet for this question.