During a validation site survey, you realize that the installers mounted some of the APs on the wait when the design called Tor a celling mount. They said that this was done because the cabling…

The correct answer is D. Advise the stakeholder that requirements will not be met and a new design process will be. See the full explanation below for the reasoning.

Question

During a validation site survey, you realize that the installers mounted some of the APs on the wait when the design called Tor a celling mount. They said that this was done because the cabling company did not have the right tools to run the cables above the ceiling. You know that this will cause a difference in how the Wi-Fi signal will radiate throughout the environment. What should you do in this case?

Options

  • ALeave it as it is because it will not have a significant impact
  • BBlame the cabling company it the Wi-Fi doesn't work since they did not do their job correctly
  • CTurn up the power on the APs to accommodate for the difference
  • DAdvise the stakeholder that requirements will not be met and a new design process will be

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    9% (2)
  • C
    4% (1)
  • D
    74% (17)