Even when a full pre-design site survey is not performed, what is always recommended to be performed within the deployment areas?

The correct answer is A. A spectrum analysis walkthrough. See the full explanation below for the reasoning.

Question

Even when a full pre-design site survey is not performed, what is always recommended to be performed within the deployment areas?

Options

  • AA spectrum analysis walkthrough
  • BAn AP-on-a-stick survey of 37% of the facility as this amount provides all of the statistical
  • CA scan m the 5 GHz band looking for common loT interferes
  • DA scan in the Sub-i GHz bands to determine If sideband interference will impact 2 4 GHz

How the community answered

(60 responses)
  • A
    80% (48)
  • B
    7% (4)
  • C
    12% (7)
  • D
    2% (1)