CWDP-305 · Question #164

Before performing a pre-deployment passive RF survey of a new deployment using survey mapping software, which of the following must be performed?

The correct answer is B. Scaling the map. See the full explanation below for the reasoning.

Question

Before performing a pre-deployment passive RF survey of a new deployment using survey mapping software, which of the following must be performed?

Options

  • ADetermining AP transmit power
  • BScaling the map
  • CSelecting antennas
  • DChecking client DTPC settings

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    71% (25)
  • C
    17% (6)
  • D
    9% (3)