Which document provided to your customer should include all devices and parts that are going to be used during the deployment of their WLAN infrastructure?
The correct answer is B. BoM. See the full explanation below for the reasoning.
Question
Which document provided to your customer should include all devices and parts that are going to be used during the deployment of their WLAN infrastructure?
Options
- ASoW
- BBoM
- CDesign report
- DProject plan
How the community answered
(32 responses)- A3% (1)
- B81% (26)
- C3% (1)
- D13% (4)