CWDP-302 · Question #69

Given: In a site survey deliverable report, you are expected to explain the spectrum measurements taken at the customer's site. What portion of a spectrum analyzer view can be used to determine if a…

The correct answer is D. Duty cycle. See the full explanation below for the reasoning.

Question

Given: In a site survey deliverable report, you are expected to explain the spectrum measurements taken at the customer's site. What portion of a spectrum analyzer view can be used to determine if a given channel is too active for use as the active channel for a new AP?

Options

  • ADevice list
  • BFrame decode
  • CReal time FFT
  • DDuty cycle

How the community answered

(51 responses)
  • A
    6% (3)
  • B
    12% (6)
  • C
    2% (1)
  • D
    80% (41)