CV0-004 Question #316: Real Exam Question with Answer & Explanation
The correct answer is C: Work breakdown structure. The Work Breakdown Structure (WBS) is the hierarchical decomposition of deliverables into smaller, manageable work packages. If tasks need to be split into smaller deliverables, the WBS is the document to update first. Risk assessments and milestone charts serve other purposes.
Question
A project team is reviewing the project plan and related documents and identifies tasks that could be spread into smaller deliverables. Which of the following documents should the team edit first?
Options
- ARisk assessment
- BPreliminary scope statement
- CWork breakdown structure
- DMilestone chart
Explanation
The Work Breakdown Structure (WBS) is the hierarchical decomposition of deliverables into smaller, manageable work packages. If tasks need to be split into smaller deliverables, the WBS is the document to update first. Risk assessments and milestone charts serve other purposes.
Topics
Community Discussion
No community discussion yet for this question.