The correct answer is B: An active-active site.. Active-active configurations involve multiple sites operating simultaneously, ensuring maximum availability and failover capabilities, which are critical for meeting high SLA requirements.
Question
A SaaS provider wants to maintain maximum availability for its service. Which of the following should be implemented to attain the maximum SLA?
Options
- AA mobile site.
- BAn active-active site.
- CA warm site.
- DA cold site.
Explanation
Active-active configurations involve multiple sites operating simultaneously, ensuring maximum availability and failover capabilities, which are critical for meeting high SLA requirements.