An organization is conducting a performance test of a public application. The following actions have already been completed: - The baseline performance has been established - A load test has passed. -

The correct answer is D. Conduct a test with the end users and collect feedback.. The purpose of a performance test is to assess the performance of an application under a variety of conditions. The goal is to identify any potential bottlenecks or performance issues that could impact the user experience.

Operations and Support

Question

An organization is conducting a performance test of a public application. The following actions have already been completed:

  • The baseline performance has been established
  • A load test has passed.
  • A benchmark report has been generated

Which of the following needs to be done to conclude the performance test?

Options

  • AVerify the application works well under an unexpected volume of requests.
  • BAssess the application against vulnerabilities and/or misconfiguration exploitation.
  • CTest how well the application can resist a DDoS attack.
  • DConduct a test with the end users and collect feedback.

How the community answered

(61 responses)
  • A
    7% (4)
  • B
    15% (9)
  • C
    3% (2)
  • D
    75% (46)

Explanation

The purpose of a performance test is to assess the performance of an application under a variety of conditions. The goal is to identify any potential bottlenecks or performance issues that could impact the user experience.

Topics

#performance testing#user acceptance testing#load testing#benchmarking