CV0-003 · Question #157
Implementing a process in a change management system takes place after:
The correct answer is D. approval by the CAB. In ITIL-based change management, formal CAB approval is the authorization gate that must be passed before any change is implemented in the production environment.
Question
Implementing a process in a change management system takes place after:
Options
- Arigorous peer review.
- Bconsultation with the vendor.
- Cinitial test in a sandbox.
- Dapproval by the CAB.
How the community answered
(32 responses)- A3% (1)
- C6% (2)
- D91% (29)
Why each option
In ITIL-based change management, formal CAB approval is the authorization gate that must be passed before any change is implemented in the production environment.
Peer review is part of the change assessment and design phase, which occurs well before the CAB authorization that directly precedes implementation.
Vendor consultation may inform change planning or evaluation, but it is not the formal authorization checkpoint required to unlock implementation.
Sandbox testing validates the change and feeds into the CAB review, but a successful test alone does not authorize implementation - CAB approval is still required.
The Change Advisory Board (CAB) is the governing authority responsible for evaluating risk, impact, and scheduling before authorizing changes to proceed. Under ITIL change management, implementation is only permitted after the CAB grants formal approval, ensuring that all relevant stakeholders have reviewed and accepted the change plan.
Concept tested: ITIL change management CAB authorization workflow
Source: https://www.axelos.com/certifications/itil-service-management/itil-4-foundation
Topics
Community Discussion
No community discussion yet for this question.