CV0-002 · Question #413
A cloud administrator has to migrate from an on-premises to a public cloud. The administrator has 20 physical servers and 600 virtual instances to migrate within a month. Which of the following should
The correct answer is A. The maintenance window, network bandwidth, and virtual instances sizes.. To effectively migrate 20 physical servers and 600 virtual instances to a public cloud within a month, an administrator must analyze key operational and technical factors.
Question
A cloud administrator has to migrate from an on-premises to a public cloud. The administrator has 20 physical servers and 600 virtual instances to migrate within a month. Which of the following should the administrator analyze?
Options
- AThe maintenance window, network bandwidth, and virtual instances sizes.
- BThe virtual instances sizes, archive repository size, and maintenance window.
- CThe network bandwidth, systems restore point, and virtual instances sizes.
- DThe backup window, network bandwidth, and virtual instances sizes.
How the community answered
(60 responses)- A78% (47)
- B12% (7)
- C3% (2)
- D7% (4)
Why each option
To effectively migrate 20 physical servers and 600 virtual instances to a public cloud within a month, an administrator must analyze key operational and technical factors.
The maintenance window defines the acceptable downtime for cutovers, network bandwidth determines the speed and feasibility of transferring 620 instances' data, and virtual instance sizes dictate the total data volume and destination resource requirements in the cloud. These are fundamental considerations for planning a large-scale, time-sensitive migration.
Archive repository size is irrelevant for migrating active production servers and virtual instances to a public cloud.
System restore points are primarily for local system recovery and not a central planning factor for migrating entire instances to a new cloud environment.
While backups are crucial, the backup window is less directly impactful on the migration execution timeline than the specific maintenance window reserved for the migration process itself.
Concept tested: Cloud migration planning factors
Source: https://learn.microsoft.com/azure/migrate/migrate-services-overview