nerdexam
CompTIA

CV0-002 · Question #310

In a private cloud environment, which of the following is the BEST way to update 20 VMs with the same patch that has been regression tested and approved for rollout?

The correct answer is D. Install the patch on as many VMs as possible during the next maintenance window.. For an approved patch on 20 VMs in a private cloud, the most effective method is to apply it to as many VMs as possible during a maintenance window.

Deployment

Question

In a private cloud environment, which of the following is the BEST way to update 20 VMs with the same patch that has been regression tested and approved for rollout?

Options

  • AAutomate the distribution of the patch and use an orchestration tool to roll it out.
  • BRoll out the patch manually to the 20 VMs and reboot the system.
  • CDeploy the patch to ten VMs for testing and then install it on the remaining VMs.
  • DInstall the patch on as many VMs as possible during the next maintenance window.

How the community answered

(39 responses)
  • A
    8% (3)
  • B
    13% (5)
  • C
    3% (1)
  • D
    77% (30)

Why each option

For an approved patch on 20 VMs in a private cloud, the most effective method is to apply it to as many VMs as possible during a maintenance window.

AAutomate the distribution of the patch and use an orchestration tool to roll it out.

While automation and orchestration tools are ideal for efficient patch deployment, simply stating to "automate the distribution" and "use an orchestration tool" does not fully describe the operational strategy for applying an approved patch within a production environment, specifically neglecting the importance of a maintenance window.

BRoll out the patch manually to the 20 VMs and reboot the system.

Manually patching 20 VMs is inefficient, prone to human error, and does not scale well in a cloud environment.

CDeploy the patch to ten VMs for testing and then install it on the remaining VMs.

The patch has already been regression tested and approved for rollout, making additional testing on a subset of VMs redundant before general deployment.

DInstall the patch on as many VMs as possible during the next maintenance window.Correct

Since the patch has been regression tested and approved, the most efficient and least disruptive method for a production environment is to apply it to as many VMs as feasible within the designated maintenance window. This approach minimizes service disruption while maximizing patch compliance.

Concept tested: Patch management strategy for approved updates

Source: https://learn.microsoft.com/en-us/azure/update-manager/overview

Topics

#Patch management#Orchestration#Private cloud operations